• 0151 343 1963

  • Cold Water Tank Replacement

    This is one of those jobs that plays to the strengths of the Kimpton team. It’s a project to replace a 40,000 gallon (180m3) cold water tank on an industrial site. Our aim was to minimise disruption to the production plant it supplies, by working to agreed hours, with scheduled mini-shutdowns.

    The old tank was fibreglass and the integrity of the seals between panels had started to break down. In addition, cleaning the tanks, which needs to happen annually, was a major job. The issue was the lack of low-level access, which meant it had to be treated as a confined space and therefore fully scaffolded before cleaning could begin.

    The job began by draining and decommissioning the tank. A large access hole could then be cut so we could work safely inside the tank. The job of dismantling the panels involved the removal of nearly 3,000 individual nuts and bolts. We previously replaced the cold water tank at the Capital Building.

    The existing pipework removed was all 6″ copper pipework – so of a very large scale.

    With this removed we could begin to install all of the new bracketry and prefabricated stainless steel Type 316L Schedule 10S pipework, ready for the tank.

    With the preparation completed, the installation of the new GRP tank began. Because of changing demand and more efficient water management on site, it was smaller at 25,000 gallons (96m3) and also met more recent legislation in terms of low-level access to make ongoing cleaning far easier.

    The tank was chemically cleaned and chlorinated before being filled from the newly installed pipework. With all of this done, the tank was brought online.

    The water level in the new tank is measured by a sonar which feeds the information into a BMS. The inflow of water is delivered through an equilibrium ball valve. As a further back-up, there is an early warning 3/4″ pipe to warn of potential overflows with an additional 6″ overflow near the top of the tank.

    To prevent freezing anywhere in the system there are also two immersion heaters inside the tank and trace heaters on the incoming pipework, again linked to the BMS.

    The job looks great, works perfectly and was completed in under five weeks.

    «Back to Blog

    What our customers say

    • Kimpton Energy Solutions have provided a reliable and helpful service at Dover and Philharmonic Court since they were opened in 2014 /15. A good working relationship is maintained with the service engineers and having a key account manager who is responsive and maintains regular communication has been a key factor in service provision.Having a…

    • Kimptons provided a ‘planned maintenance schedule’ to suit our academic year requirements and maintained the dates set out. Their engineers were always well presented and aware of how to conduct themselves within our environment. They were all trained and knowledgeable on the various items of equipment they came to work on. Mr Mike Pickles,…

    • We are happy with the service Kimptons have provided over the years. Their engineers are local and have great knowledge of our systems. We have built up an excellent working relationship with service engineers along with their office staff. Mr Kevin Foy, Notre Dame College

    • The Kimpton engineers on site are always accommodating to requests from the estates team with regards to heating, ventilation and air conditioning issues. The planned maintenance schedule has developed over the years and works well throughout the year. Having a key account manager who attends site on a weekly basis provides an excellent line…

    • The installation will improve the comfort conditions in several areas of the school servicing both pupils and staff. We are very experienced in undertaking projects in these conditions were flexibility and careful scheduling is key and this was crucial to our appointment on this contract.

    • We have been using TKR Services since their inception and during that time they proved to be not only commercially competitive, but also, looking from an Engineers point of view they have strived to provide the highest quality work.

    • The Plaza is a showpiece building for Bruntwood in Liverpool and we have since made it our own headquarters in the city. To reflect this, we needed to ensure that the fit out was of the highest quality, whilst maintaining the high levels of service our tenants expect from Bruntwood.