• 0151 343 1963

  • Major Plant Removal for Hospital Roof Replacement

    The Kimpton Maintenance team are currently on-site, working alongside a major roofing contractor to remove the air conditioning plant, to allow them to complete the replacement of the ageing roof.

    As you can see from the Google Maps images below, the roof is huge and stretches across twelve separate buildings, with a mix of flat and pitched roof spaces. There are 31 individual units to be removed and a large air handling unit (AHU) too. The project has thrown up a number of challenges, most of which could be anticipated and a few that required a little creative thinking.

    One of the biggest is in removing the 1.5-ton AHU that’s positioned between two of the buildings with no road access. You can see it marked here below. This entails a lift from a 4-ton crane to remove it and place it on the grassed area, whilst the roof works take place. Why do we need a 4-ton crane for a 1.5-ton lift? It’s all to do with the outreach. You can see in the image, the semi-permanent placement of the MRI truck. This is where we will position the crane. Even getting as close as we can to the AHU, there’s still a 34m reach required to lift and relocate it to safety.

    Roof replacement with 31 ac units showing crane positioning

    The second major challenge, as we have discussed a lot over recent years, is in having to condemn working air conditioning units. These units, filled with the now obsolete (and outlawed) R22 gas, can no longer be recommissioned. Some of these will be replaced with more energy-efficient units. Others will not be replaced where there’s been a change of use in the space they serve, and air conditioning is no longer required.

    The third challenge, which is absolutely specific to the healthcare sector, is that some of the units could only be offline for a very short period of time as they serve the operating and critical care areas of the hospital. In these instances, we work very closely with our roofing partners, to remove, replace the roof and refit the units in under 24 hours.

    We’re always happy to take on challenging jobs like this – even ones where there are critical timescales. Being able to provide solutions like this, with potential for problems at every turn is not everyone’s cup of tea. Being comfortable doing so, is a definite benefit of experience. To do so, you do need a partner you can trust and we believe that at Kimptons, we are that partner. Together we could be brilliant.

    «Back to Blog

    What our customers say

    • Kimpton Energy Solutions have provided a reliable and helpful service at Dover and Philharmonic Court since they were opened in 2014 /15. A good working relationship is maintained with the service engineers and having a key account manager who is responsive and maintains regular communication has been a key factor in service provision.Having a…

    • Kimptons provided a ‘planned maintenance schedule’ to suit our academic year requirements and maintained the dates set out. Their engineers were always well presented and aware of how to conduct themselves within our environment. They were all trained and knowledgeable on the various items of equipment they came to work on. Mr Mike Pickles,…

    • We are happy with the service Kimptons have provided over the years. Their engineers are local and have great knowledge of our systems. We have built up an excellent working relationship with service engineers along with their office staff. Mr Kevin Foy, Notre Dame College

    • The Kimpton engineers on site are always accommodating to requests from the estates team with regards to heating, ventilation and air conditioning issues. The planned maintenance schedule has developed over the years and works well throughout the year. Having a key account manager who attends site on a weekly basis provides an excellent line…

    • The installation will improve the comfort conditions in several areas of the school servicing both pupils and staff. We are very experienced in undertaking projects in these conditions were flexibility and careful scheduling is key and this was crucial to our appointment on this contract.

    • We have been using TKR Services since their inception and during that time they proved to be not only commercially competitive, but also, looking from an Engineers point of view they have strived to provide the highest quality work.

    • The Plaza is a showpiece building for Bruntwood in Liverpool and we have since made it our own headquarters in the city. To reflect this, we needed to ensure that the fit out was of the highest quality, whilst maintaining the high levels of service our tenants expect from Bruntwood.