Replacement heating and cooling system for the Capital Building

The Capital Building, or to use its original name, New Hall Place, is a 13 storey building in the Commercial District in Liverpool. Because of its sandy-coloured exterior and waterfront location, it’s often known locally, as the Sand Castle. Originally built in 1974 for Royal Insurance, it incorporates a section of the original ‘walkways in the sky’ project that began with the Shankland Plan for Liverpool city centre in 1965 and ended slightly ignominiously when the last sections were closed off or removed in 1995.

The building was always well ahead of its time, in the way it used water sourced heat pumps. The system is fed with the three thousand gallons of water per hour that seeps into the Mersey Railway Tunnel from the river above. This water, which enters at a year-round, constant 13 degrees centigrade is then used to either heat the building, or as a heat sink to cool the building.

But any system, however ahead of its time does need to be replaced when it’s reached the end of its efficient life.

Enter Kimpton

The project we have taken on is broken up into three main parts.

  • Firstly to create a temporary heating and cooling system for the building, so the aged pipework can be replaced.
  • When this is completed, we will strip out and replace all of that pipework from the top floor right through to sub-basement level
  • Then it’ll be time to install the new system and to remove the temporary solution.

These three phases are expected to take around 12 months to complete.

Work is currently underway to install the temporary dry air coolers. These are being installed on the Fazakerley Way walkway and when complete will feed into the plant room on the sub-basement level of the building. We’ll be using pre-insulated Cool Fit Pipework, which is a relatively lightweight solution, has superb thermal properties and allows for quick installation/removal.

One small point to share here is that in some of the images, you can see one of our newer apprentices, Josh Anderson, hard at work on the project. Josh joined us after completing a successful work placement from school.

 

The project faces a number of key challenges:

  • We’re working on a live site which is home to the UK Border Agency and Royal Sun Alliance, so security, whilst keeping the offices functioning as normal, is critical.
  • We’re working within COVID-19 guidelines to ensure we keep our staff, our clients and their own customers safe too.
  • Access is difficult – We’re working across multiple levels, outdoor roof spaces and sub-basement plant rooms.
  • The size of the pipework is significant as it is designed to feed an entire 13 storey building.
  • We must cause minimal disruption so we’re working out of hours where required, to allow the building users continuity of access.

We hoisted the three-tonne dry air coolers into position on Fazakerley Way (one of the original walkways at fourth-floor level) on a Saturday. A full road closure was called for. The contract lift was completed without incident.

 

It’s a project with obvious challenges, but just the type of work we really enjoy. We’ll share more images as the project progresses.

In the meantime, here are a few pictures to allow you to enjoy the view from the top of the building and New Quay Terrace, another of the sky walkways.

 

Creating the
sustainable building
environments of tomorrow

Quick enquiry

If you would like to discuss any of our services, please call 0151 343 1963 or complete the form below and we will be in touch shortly.

    Creating the
    sustainable building
    environments of tomorrow