• 0151 343 1963

  • New Chillers for Countess of Chester

    The Kimpton team recently completed a project at the Countess of Chester Hospital to remove redundant plant and completely refit the chiller system that serves the main operating theatres, five of the wards, the recovery area, pharmacy along with the intensive care unit.

    The project began in January on a 12-week programme to coincide with the time when the requirement for chillers in these critical areas of the hospital was at the absolute minimum.

    The original system, installed in the 1970’s, was inefficient, noisy and unreliable.

    The first part of the job was the mechanical strip out. This involved the removal of the Packaged water cooled Chiller Units in the plant room and the Remote Air Cooled Condensers on the roof. There were also primary and secondary pumps, along with buffer vessels and expansion tanks. The pipework in the plant room was stripped back as far as required, but the new system being installed had been designed to fit into and utilise the existing air handling units within the hospital itself.

    This did involve some challenges as these units were very heavy and access was limited. The removal was completed partly by hand carrying the units out of the site and utilising the goods lift when it was available for the items that physically could not be hand-carried down the stairs.

    The second stage was to make good some of the builders work required and then finally paint the plantroom floors throughout to allow easier cleaning and maintenance going forwards. When you look at some of the ‘before’ images, you will see why this was required.

     

    With the plant room and roof space ready for the new plant, our work began. The chillers being installed were two Daikin 180kW EWAT R32 chillers. These are the latest generation of chillers and compared to the previous R-410 equipped models, have a 66% improved GWP (Global Warming Potential).

    The system was upgraded to deliver the same chilled water cooling demand of the previous system, but with more resilience in case of failure. The final system in fact delivers 100% redundancy so that even if one of the chillers should fail, or be offline for maintenance, the chilling power is still delivered to the essential hospital wards and theatres.

    With the chiller units being fitted on the roof of a live hospital environment, it was important to reduce vibration from the chiller units in operation. In order to achieve this, they were fitted onto anti-vibration mounts.

    To ensure the longevity and ongoing performance of the system, the system is fitted with a DosaFil Duo side stream filter. This in itself is extremely high performing and has inbuilt water quality monitoring. If the system detects a full filter or iron particles reaching too high a level, it doses the system and flags it on the BMS. (Building Monitoring System)

    The photos below show the new chillers on the rooftop and the new insulated pipework. These pass down into the plantroom where you can see the new pump sets and the Dodsafil filtration system.

     

    Electrical fit-out

    In addition to the mechanical fit-out, there were also all of the electrical works associated with the project. These included all of the work for the BMS and the motor controls. In addition, there was work to complete the containment, earning and bonding, testing and commissioning and the lighting for the plant room. The final stage was the modification and upgrade to the lightning protection.

    Summary

    The 12-week project was completed on time and within the £270k budget and is working well on site. This sort of project is one that plays to the strengths of Kimpton. We are experts in projects where mechanical and electrical services work hand in hand. When there is an element of improving efficiency or decarbonisation, we have experience stretching back to the early 1970s, before the term decarbonisation had even been coined.

     

     

     

    «Back to Blog

    What our customers say

    • Kimpton Energy Solutions have provided a reliable and helpful service at Dover and Philharmonic Court since they were opened in 2014 /15. A good working relationship is maintained with the service engineers and having a key account manager who is responsive and maintains regular communication has been a key factor in service provision.Having a…

    • Kimptons provided a ‘planned maintenance schedule’ to suit our academic year requirements and maintained the dates set out. Their engineers were always well presented and aware of how to conduct themselves within our environment. They were all trained and knowledgeable on the various items of equipment they came to work on. Mr Mike Pickles,…

    • We are happy with the service Kimptons have provided over the years. Their engineers are local and have great knowledge of our systems. We have built up an excellent working relationship with service engineers along with their office staff. Mr Kevin Foy, Notre Dame College

    • The Kimpton engineers on site are always accommodating to requests from the estates team with regards to heating, ventilation and air conditioning issues. The planned maintenance schedule has developed over the years and works well throughout the year. Having a key account manager who attends site on a weekly basis provides an excellent line…

    • The installation will improve the comfort conditions in several areas of the school servicing both pupils and staff. We are very experienced in undertaking projects in these conditions were flexibility and careful scheduling is key and this was crucial to our appointment on this contract.

    • We have been using TKR Services since their inception and during that time they proved to be not only commercially competitive, but also, looking from an Engineers point of view they have strived to provide the highest quality work.

    • The Plaza is a showpiece building for Bruntwood in Liverpool and we have since made it our own headquarters in the city. To reflect this, we needed to ensure that the fit out was of the highest quality, whilst maintaining the high levels of service our tenants expect from Bruntwood.