Case Studies

Merseyside Joint Command Centre, Bootle

Merseyside Joint Command Centre, Bootle

Project Details

The Client: Merseyside Fire & Rescue Service
Customer: Kier Construction
Service: Mechanical & Electrical
Project Value: £2.9m
Project Completion: July 2014

The Project

This landmark project in Merseyside brought together both Merseyside Fire and Rescue Service and Merseyside Police in a Joint Command Centre. The new development saw the extension of the existing Merseyside Fire & Rescue Services Head Office in Bootle being extended to provide a Command Centre of over 100 positions for both Fire and Police for both call handling and emergency despatch operators.

The project involved the design, supply, installation, testing and commissioning of the Mechanical Services to serve the proposed new Merseyside Joint Control Centre building which includes both an element of new build and an element of existing building refurbishment.

Merseyside Joint Command and Control Centre 2

Scope of Works

The full extent of the mechanical services work was extremely broad and included the following areas of work for the Kimpton team.

  • Natural gas infrastructure.
  • Mains cold water infrastructure.
  • LTHW heating services.
  • VRF/VRV heating and cooling installations.
  • DX cooling installations.
  • Domestic hot and cold water installations.
  • Mechanical and natural ventilation installations.
  • Automatic controls systems installations.
  • Thermal insulation services.
  • Above ground drainage installation.

In addition to the above, we were also tasked with delivering the building to achieve a BREEAM ‘Very Good’ rating and we had to provide all information and installations as required to achieve the M&E related credits.

Success of the project

Kimpton were brought in as part of the design team at the early stages of the project to develop the full M&E design.

The mechanical services comprised primarily a Mitsubishi VRF system to heat and cool the building, with communal areas heated from an existing LTHW boiler plant and DHWS provided by way of Point of Use water heaters due to the potential long pipe runs. Kimpton also provided a full misting system and 2 gaseous extinguishing systems for fire control within the building and the 2 server rooms respectively.

The electrical services involved the development, from concept to full implementation, of a fully maintained diverse power supply. The LV supply to the building was determined to be insufficient to cope with the peak maximum demand in case of a major incident and the command centre was fully manned. A series of LV switchboards coupled with two standby generators, to be operated sequentially or in parallel and for both emergency supply, in the case of HV power failure and also for maximum demand. Due to the critical nature of the buildings function, the IT system is split across 2 internal data centres both supplied with dual UPS supplies in the case of mains power failure.

Within the electrical services package, Kimpton also provided full fire detection system, external lighting and internal lighting system with lighting control system. CCTV and Access control was provided to the Polices’ security levels along with all small power and IT infrastructure.

Merseyside Joint Command and Control Centre

Creating the
sustainable building
environments of tomorrow

Quick enquiry

If you would like to discuss any of our services, please call 0151 343 1963 or complete the form below and we will be in touch shortly.

    Creating the
    sustainable building
    environments of tomorrow