Case Studies

Biomass Upton by Chester High School

Biomass Upton by Chester High School

Project Details

The Client: Upton by Chester High School
Customer: Mathieson Biomass
Service: Biomass Boiler
Project Value: £163,000
Project Completion: January 2014

The Project

As part of their drive to reduce their carbon footprint and save money on energy consumption the school committed to upgrading their heating system.

A 350kW pellet fired biomass boiler was installed as the primary source of heating and connected into the existing primary heating system. The existing control system was modified to accept the Biomass Boiler as the lead boiler, with the additional heating load picked up by the existing gas fired boilers in the winter months.

The Biomass system complete with pellet bag silo and 4,000 litre buffer tank was installed within a purpose built plantroom to house the new plant.

Creating the
sustainable building
environments of tomorrow

Quick enquiry

If you would like to discuss any of our services, please call 0151 343 1963 or complete the form below and we will be in touch shortly.

    Creating the
    sustainable building
    environments of tomorrow