Rochdale National Grid Transformer

Rochdale National Grid Transformer

Project Details

The Client: National Grid
Customer: Morgan Sindall
Service: Acoustic Enclosure
Project Completion: February 2013

The Project

Kimpton were employed by Morgan Sindall to assist them in meeting the noise emissions criteria set out in the planning permission for the replacement transformer.

A noise impact assessment determined that an insertion loss of 20dB @ 100Hz was required for the new transformer to alleviate the potential noise disturbance to local residents.

Kimpton Acoustics designed, manufactured and erected a new acoustic enclosure. As this is a live site and the new transformer was a replacement the enclosure had to be erected within a 2 week period. Along with housing the transformer the new enclosure had to accommodate a deluge system in the case of fire.

Creating the
sustainable building
environments of tomorrow

Quick enquiry

If you would like to discuss any of our services, please call 0151 343 1963 or complete the form below and we will be in touch shortly.

    Creating the
    sustainable building
    environments of tomorrow